Bengaluru’s Nandi Hills cable car project set for 2027 completion

Bengaluru’s long-awaited Nandi Hills ropeway is moving forward, with land acquisition nearly complete, approvals underway, and civil work expected by early 2025. Completion is targeted for mid-2027.

author-image
Dhanya Reddy
CABLE CAR IN NANDI HILLS
Advertisment
  • 2.9 km ropeway to connect lower and upper terminals at Nandi Hills
  • 50 semi-closed cabins offering panoramic hill views
  • Completion targeted by mid-2027, pending forest clearance

After decades of planning, the 2.9 km cable car project aims to transform tourism at Nandi Hills, offering panoramic views and modern facilities.

The ambitious Nandi Hills cable car project in Bengaluru is finally taking shape, with completion projected by mid-2027. The land acquisition for the upper terminal, covering 3.5 acres of private property, is expected to conclude by November, clearing a major hurdle.

Also Read:Here’s how you can apply for B-Khata to A-Khata conversion and also get A-Khata for new sites!

The 2.9-kilometre ropeway, a public-private partnership with Dynamicx Ropeway Private Limited, will feature 50 semi-closed cabins, ferrying visitors between lower and upper terminals while offering panoramic views of the hills.

The lower terminal will include parking for 200+ cars, 110 two-wheelers, and multiple buses, alongside a waiting area for up to 600 people. Civil work is expected to commence by the end of this year or early 2025, with a 1.5-year construction timeline.

Also Read:BBK 12: Rashika and Kavya battle for last finalist spot! Who gets it?

The final regulatory challenge involves forest clearance, as one supporting pillar falls within forest land. Once this is resolved, the ropeway will provide a modern, scenic experience at one of Karnataka’s most popular tourist destinations.